Monday, April 28, 2008

Decking and Fill

VanOverberghe's began framing last week and put up the floor trusses and most of the decking.

Matt spent the day there Saturday bringing in sand. I guess 350 tons of fill was delivered and he and Chris and Grant Hemminger worked all day and it's not quite done. The girls and I ran over to deliver the guys Subway and then came back later with freshly baked cookies, but we didn't stay because the weather really cooled off (and we're spoiled from the warm weather last week).
Here are some pictures taken from the road.

Tuesday, April 22, 2008

Floor Poured - Framing Started

I haven't posted on the house in a while. It is making progress but April started out a rainy month (and we had a baby!) so progress was slowed. Just after bringing Carolyn and I home from the hospital, Matt was able to get the floor poured in the basement. He's also been over there still cleaning brush and using his chainsaw on all the poor ugly trees.

Here's a picture of the basement floor poured - I admit, it's mainly a picture of our little Carolyn, but through the window you can clearly see the floor. This is Carolyn's first trip to the site of her future home.

And this week the framers are coming in to start the framing! So we'll be making huge progress soon. They will take 4 to 6 weeks to complete, weather dependant.